HomeMy WebLinkAboutIX-01 Award Contract - Mississippi River Trail Erosion Repair City Council Memorandum To: Mayor Fasbender & City Councilmembers From: Chris Jenkins, Parks & Recreation Director Date: August 5, 2024 Item: Mississippi River Trail Erosion Repair Council Action Requested: Award contract and execute attached Notice of Award. Background Information: A section of the Mississippi River bank has been slowly eroding away, and it became a major safety issue in 2023. At the February 5, 2024 regular City Council meeting council approved and authorized funding for the design and engineering of the repair project. Barr Engineering was hired to complete this process, and have been working since that time to complete the D&E, permitting and bidding of this project. On July 23, 2024 bids were received and opened, with Fitzgerald Excavating & Trucking Inc. submitting a complete bid meeting all of the requirements and with the lowest cost at $49,515.00. This project is a bit dependent upon water levels in the Mississippi River, however substantial completion is set for September 27, 2024 with final completion for October 11, 2024. Staff and consultant recommend awarding this contract to Fitzgerald Excavating & Trucking Inc. and execute the attached Notice Of Award. Financial Impact: As with the design and engineering, this expense was a bit unexpected yet necessary to maintain trail user safety and retain existing trail infrastructure. Council approved using Fund Balance from Fund 200 for the D&E, and staff suggest the same funding source for this project. An important note here, since the Mississippi River Trail is part of Dakota County’s Regional Trail System, County staff are supportive of a cost share for the project with a proposed 40% County cost and 60% City cost for the entire project. County staff will be presenting this proposal to the County Board in August. Design and Engineering Costs were funded at $27,300.00, and the repair project bid cost of $49,515.00 bring the total project cost to $76,815.00. A 40/60 cost share would bring the City total to $46,089.00 to complete this project. IX-01 Advisory Commission Discussion: N/A Council Committee Discussion: N/A Attachments: ▪ Recommendation Letter ▪ Notice to Proceed IX-01 barr.com 4300 MarketPointe Drive, Suite 200, Minneapolis, MN 55435 | 952.832.2600 Memorandum To: City of Hastings From: Barr Engineering Co. Subject: Mississippi Riverbank Repair Bid Recommendation Date: July 31, 2024 Project: 23/19-1527.00 Dear Mr. Jenkins, On Tuesday, July 23, 2024, bids for the Mississippi Riverbank Repair project were received. The following quotes were acknowledged for the project. Contractor Bid Total Fitzgerald Excavating & Trucking Inc. $49,515.00 Sunram Construction, Inc. $73,105.00 Hoffman & McNamara Co. $77,797.00 Shoreline Landscaping, LLC $94,100.00 JL Theis, Inc. $113,950.00 Rachel Contracting, LLC $119,005.00 US Sitework, Inc. $123,182.00 Engineers Estimate $62,410.00 Fitzgerald Excavating & Trucking Inc. submitted the lowest quote price of $49,515.00. Fitzgerald’s submittal complies with all the requirements of the Contract Documents, and we recommend acceptance of the quote. Upon Council’s acceptance of the quote, we will send the Notice of Award to the contractor and request that they provide insurance information and sign the Form of Agreement. Work will commence at the site after the Form of Agreement has been executed by all parties and the Notice to Proceed issued. Fitzgerald has until Wednesday, September 27, 2024 to be substantially complete, and until Wednesday, October 11, 2024 for final completion. If you have any questions, please contact me at 952-842-3593 or pbrockamp@barr.com. Sincerely, Pat Brockamp, PE IX-01 City of Hastings Notice of Award Mississippi Riverbank Repair Page 1 of 1 NOTICE OF AWARD MISSISSIPPI RIVERBANK REPAIR OWNER: City of Hastings Dated: July 31, 2024 TO CONTRACTOR: Fitzgerald Excavating & Trucking, Inc 21432 350th Street Goodhue, MN 55027 CONTRACT FOR: Mississippi Riverbank Repair Project Owner has requested that we notify you that your Bid dated July 23, 2024 has been accepted as the successful Bidder and Fitzgerald Excavating & Trucking, Inc (Fitzgerald) has been awarded the contract to perform the Work. The Contract Price is stated in the Agreement. Fitzgerald must comply with the following conditions precedent within fifteen (15) days of the date of this Notice of Award, that is by August 16, 2024. 1. Return to Owner a digital copy of the fully executed Agreement (attached). 2. Certificate of Insurance naming the City of Hastings and Barr Engineering Co. as additional insured. Failure to comply with these conditions within the time specified will entitle Owner to consider your bid in default, to annul this Notice of Award and to declare your Bid Security forfeited. END OF DOCUMENT OWNER: By: (AUTHORIZED SIGNATURE) ACKNOWLEDGEMENT OF NOTICE CONTRACTOR By: (AUTHORIZED SIGNATURE) (TITLE) (DATE) IX-01