HomeMy WebLinkAboutVIII-09 Approve Change Order No. 3 to the Public Works Storage Building City Council Memorandum
To: Mayor Fasbender & City Council Members
From: Ryan Stempski – Public Works Director/City Engineer
Date: October 12, 2022
Item: Approve Change Order No. 3 for the Hastings Public Works Storage Building
COUNCIL ACTION REQUESTED
Council is requested to approve attached Change Order No. 3 for the Hastings Public Works Storage Building
Project.
BACKGROUND INFORMATION
Change Order No. 3 covers the cost of aggregate base requested by the City to be placed in lieu of recycled
aggregate base allowed in the project specifications.
FINANCIAL IMPACT
The value of the work contemplated by Change Order No. 3 is an increase of $1,439.15.
Below is a table summarizing the change orders to date.
2022-3 Hastings Public Works Storage Building
Change
Order Date Item
Estimated
Value
1 8/22/2022 Change Order No. 1 $56,237.27
2 9/19/2022 Change Order No. 2 $10,410.03
3 10/6/2022 Change Order No. 3 $1,439.15
Net Total Increase/(Decrease) to date $68,086.45
Original Contract Value $1,310,400.00
Revised Contract Value $1,378,486.45
Change Orders as Percentage of Original Contract Value to date 5.2%
STAFF RECOMMENDATION
Staff recommends approval of attached Change Order No. 3.