PROPOSED 9TH, 101h & 11TH AND FOREST STREETS <br /> STREET & STORM SEWER CONSTRUCTION <br /> INFORMATION SHEET <br /> February 17, 2000 Open House <br /> Reconstruction Area: Oct. 2000 Complete construction <br /> 9`h Street from Maple St. to Pine St. Fall 2001 Assessment Hearing <br /> 10'hStreet from Maple St. to Pine St. Assessment Information: <br /> 11th Street from Ashland St. to Pine St. Assessments are spread over a 10 year <br /> Forest Street from 1 Vh St. to 12" St. period and are collected by Dakota <br /> Street Widths: County with your property tax. If the <br /> Existing streets will be widened to meet Council proceeds with construction ofthis project, the first assessment payment <br /> city standards. Street width will be 36 ft. would be due with your 2002 property <br /> wide(except Forest which will be 32 ft. tax payment. Interest is charge against <br /> wide) to accommodate on-street parking the remaining balance of your <br /> needs on both sides of the street. All streets assessment. The interest rate is <br /> will be constructed with concrete curb and determined by the interest rate the City is <br /> gutter. charged for the bonds that are sold to <br /> Sidewalks: finance the construction. <br /> An 5 ft. wide concrete walk is proposed to Assessment Abatement: <br /> The City has applied for Federal <br /> be constructed on the north side of 11`h St. Community Block Grant(CDBG) funds <br /> The walk will be located an average of 5 ft. for assessment abatement. Qualifying <br /> behind the curb. low income households would have their <br /> Storm Sewer: entire assessment funded by these <br /> Storm sewer will be extended from 9t'& CDBG funds. Any funds remaining after <br /> Maple to 9t'& Oak. Storm sewer will be meeting low income households <br /> extended from Wh&Pine to 30' to the east. assessment needs will be divided evenly <br /> Storm sewer will be extended from 11 1 h& among qualifying moderate income <br /> Ashland to Walnut and from 11 1 h&Maple households. <br /> to 11"&Oak. No storm sewer will be Comments: <br /> We need your comments and any <br /> installed on Forest. additional information you feel would be <br /> Why These Streets? helpful in preparing the design. This will <br /> These streets are substandard City streets, in help assure the most accurate design and <br /> poor shape and lacking concrete curb and cost estimating <br /> gutter for proper drainage. These projects Typical Assessments: <br /> are to coincide with the Roadside Park We have completed enough of the design <br /> reconstruction. process to properly estimate the <br /> Proposed Project Schedule assessments for these improvements. See <br /> March 20 Council holds public hearing to the attached sheet to for your appropriate <br /> determine if project should be location and cost figures. <br /> built. <br /> May 2000 Begin construction <br /> MAFEAS13LTY0000\a=tido1.%pd <br />